New South American Pulp Projects May Total R$109bn

March 25, 2026

After Suzano’s Cerrado project, the industry turns to a new wave of expansion in Brazil, Chile and Paraguay, led by large-scale investments in pulp capacity and logistics

With Suzano’s Cerrado project now up and running, attention in the pulp industry is shifting to new expansion plans in South America that are expected to move forward over the next five years and could add up to R$109 billion in investment.

Among the Chilean groups, Arauco has already begun construction of a mega pulp mill in Inocência, in Mato Grosso do Sul state, while CMPC is awaiting board approval to build a project in Barra do Ribeiro, in Rio Grande do Sul state. The market is also expecting the formal announcement of a new Bracell unit in Bataguassu, also in Mato Grosso do Sul, as well as Eldorado’s second line in Três Lagoas, in the same state. Paraguay’s Paracel project, by contrast, has a more uncertain future.

The outlook for pulp consumption growth, especially in Asia, along with new uses and applications for fiber, is supporting the advance of projects in the sector, said Rafael Barisauskas, Latin America economist at commodity pricing consultancy Fastmarkets.

Projects in South America are far more competitive than in most other regions of the world, particularly because of the abundant wood supply and the faster growth cycle of eucalyptus forests, about seven years in the region versus 15 years in the Northern Hemisphere. “In a worst-case scenario, in which global demand grows below expectations, the new capacity in South America would probably force higher-cost competitors out of the market,” Barisauskas said.

The region’s last major expansion moves were Bracell’s Star project, delivered in 2022 in Lençóis Paulista, São Paulo state, with R$15 billion in investment, and Suzano’s Cerrado project, completed in 2024 in Ribas do Rio Pardo, Mato Grosso do Sul. The latter received R$22 billion in investment and resulted in the world’s largest single-line eucalyptus pulp mill so far, with annual capacity of 2.55 million tonnes.

Arauco leads next wave

The project that could take that title is Arauco’s Sucuriú project. Already under construction, it is the most advanced undertaking in this new wave of mills. Backed by a $4.6 billion investment and with annual production capacity of 3.5 million tonnes of hardwood pulp, the project marks the company’s entry into Brazil’s pulp sector.

In southern Brazil, the other Chilean player, CMPC, also moved a step closer to its new pulp mill in Barra do Ribeiro by signing the concession contract for the land and construction of a private-use terminal at the Port of Rio Grande, in Rio Grande do Sul. Contracts were also signed for the construction of new vessels. Those initiatives are expected to consume about R$3 billion of the total investment planned for the mill.

The project, known as Natureza, is still awaiting environmental licenses before it can go to the board for approval. In a recent interview with Valor, Antonio Lacerda, CMPC’s pulp director, said the expectation is that this stage will be completed by midyear, paving the way for construction to begin.

Completion of the project is still expected in the second half of 2029, Lacerda said. With estimated investment of $4.6 billion the unit will have annual production capacity of 2.5 million tonnes of eucalyptus pulp.

As for forest supply, Lacerda said the company already has enough planted wood to run both of its mills in the country for five years. In addition to the new unit in Barra do Ribeiro, the Chilean company already operates a pulp mill in Guaíba, Rio Grande do Sul, with annual capacity of 2.4 million tonnes of eucalyptus pulp.

Mato Grosso do Sul expansion

Back in Mato Grosso do Sul’s so-called “Vale da Celulose” (Pulp Valley), the market expects a fifth project in the region to be announced later this year, this time by Bracell, part of Indonesia’s Royal Golden Eagle, or RGE, group. After uncertainty over the location, the company secured preliminary environmental approval in December for construction of a mill in Bataguassu.

In a statement, Bracell said it is currently carrying out the initial procedures to make a new industrial project in Bataguassu viable, in line with its economic and sustainable expansion plan in Brazil.

“The company is in the study phase and is meeting the legal requirements that support the analysis by the relevant authorities and ensure transparency in the process,” the company said. The expected completion date is the second half of 2028, although some bottlenecks could affect that schedule.

At the moment, the main issue is the lack of a power transmission line to supply the mill and carry the surplus energy it will generate. The company is awaiting the auction of a substation located 155 kilometers from the site, expected later this year, in order to secure approval for implementation of that transmission line.

With estimated investment of R$16 billion, according to the environmental impact report, the unit will have two production lines, one dedicated exclusively to pulp for paper, or kraft pulp, and another flexible line able to produce either kraft pulp or dissolving pulp, used in textile fibers, cosmetics and food.

If it produces only kraft pulp, annual capacity could reach 2.9 million tonnes. If it opts for the flexible model and produces dissolving pulp as well, output would be about 2.6 million tonnes.

“The big focus today is logistics,” said Jaime Verruck, the secretary for environment, development, science, technology and innovation in Mato Grosso do Sul. In addition to the rail modes Suzano already has in the state, and the line under construction by Arauco, Eldorado will build a 97-kilometer railway linking its mill to its terminal in Aparecida do Taboado, connecting it to Rumo’s network toward Santos. “Another point is the rebidding of Rumo’s West Network, scheduled for next year,” the secretary said.

On the road side, a consortium formed by XP and a group of builders has taken over the concession of the so-called Pulp Route, which includes a set of state and federal highway stretches in Mato Grosso do Sul. Verruck also cited Bracell’s project to use waterways to transport eucalyptus from Mato Grosso do Sul to its mill in Lençóis Paulista. “If it works well for eucalyptus, they are studying using it for pulp as well,” he said.

Another project announced for the state is Eldorado’s expansion. This is an old plan that had been suspended because of the long-running shareholder dispute between J&F, the Batista brothers’ group, and Paper Excellence. That dispute ended last year, when the Batistas bought the 49.41% stake held by Paper in the pulp producer for $2.7 billion.

According to initial estimates, the second line should require $5 billion in investment. In mid-2025, the company renewed its environmental license with Imasul, Mato Grosso do Sul’s environmental agency, and increased the project’s capacity from 2.3 million to 2.6 million tonnes of pulp a year.

The view is that the company is prioritizing debt reduction before taking the expansion plan to the board. There is also the fact that the main suppliers of equipment used in the industry are already committed to the more advanced projects.Eldorado did not comment.

Verruck said there is still room for more mills in Mato Grosso do Sul. The state has the country’s second-largest planted eucalyptus area, with 1.5 million hectares, equivalent to about 19% of Brazil’s total, according to a report by Ibá, the Brazilian Tree Industry association.

In terms of expansion, the region has been the main focus of new planting, receiving 80% of the 234,000 new hectares seen in 2024. To supply the projects already announced, another 500,000 hectares still need to be planted by the end of next year, but the government believes that target will be met.

On the other hand, Verruck acknowledged that one of the state’s main short-term challenges is housing. “It’s not the factory boom itself, because that goes into worker accommodations, it’s permanent housing to reduce turnover and keep more people in Mato Grosso do Sul,” he said.

According to him, companies have been buying land to donate to the state so it can build homes through the Minha Casa, Minha Vida (My House, My Life) affordable housing program. By 2032, an estimated 80,000 new homes are expected in Pulp Valley.

Paraguay remains uncertain

In neighboring Paraguay, Paracel continues to expand its eucalyptus planting area to supply its future mill, but the start of construction still depends on financing. The project already has 82,000 hectares under cultivation and has been planting eucalyptus at a rate of 15,000 hectares a year.

The company, controlled by Paraguay’s Zapag group, hired Jefferies to find a new investor. Austria’s Heinzel and Sweden’s Girindus are already partners in the project, which also has minority Paraguayan shareholders. But the search for this new partner, considered essential for financing the project, has not yet succeeded.

A few months ago, Paracel reached an agreement with the Inter-American Development Bank (IDB) for a potential $165 million loan. The funds would finance infrastructure works related to the project, and signing is expected in March. Paracel did not comment.

Despite this structural advantage and the fact that global supply and demand dynamics are not seen as a barrier, Barisauskas of Fastmarkets said the main obstacle for the region lies in its macroeconomic environment.

“High interest rates, especially in Brazil, tend to limit the pace and appetite for new expansion projects and for the rollout of new units across the value chain,” he said.

Source: Valor International